Resolve to investigate the results reporting of the national grid Worcester smart meter pilot program and its implications for the department of public utilities grid modernization, time of use, and smart meter proceedings
Filed by John J. Mahoney · 1 cosponsor · 191st General Court · the legislature's own page
H2888 · Resolve · docket HD3428
4 actions
In the order the legislature recorded them.
| Date | Branch | Action |
|---|
| 2019-01-22 | House | Referred to the committee on Telecommunications, Utilities and Energy |
| 2019-01-22 | Senate | Senate concurred |
| 2019-09-18 | Joint | Hearing scheduled for 09/24/2019 from 01:00 PM-05:00 PM in 437 |
| 2020-02-10 | House | Accompanied a study order, see H4405 |
Public hearing
House Rule 27 counts its reporting deadline from the day a bill is heard.
Committee actions
Cosponsors
In the order filed.
Every action here is as the legislature published it. A bill that drew no recorded vote is the ordinary case: the House records roughly 150 a year.