An Act authorizing the city of Taunton to contract for the renewal of services relative to the operation and maintenance of its wastewater treatment plant, sewers and pump stations, for a term not to exceed five years

Filed by Marc R. Pacheco  ·  3 cosponsors  ·  192nd General Court  ·  the legislature's own page

Became Chapter 105 of the Acts of 2022.

S2705  ·  Bill  ·  docket SD2998

13 actions

In the order the legislature recorded them.

DateBranchAction
2022-02-17SenateReferred to the committee on State Administration and Regulatory Oversight
2022-02-22HouseHouse concurred
2022-03-03JointHearing scheduled for 03/08/2022 from 02:00 PM-03:00 PM in Virtual Hearing
2022-03-24SenateBill reported favorably by committee and placed in the Orders of the Day for the next session
2022-04-07SenateRead second and ordered to a third reading
2022-05-09SenateTaken out of the Orders of the Day
2022-05-09SenateRead third (title changed) and passed to be engrossed
2022-05-12HouseRead; and referred to the committee on House Steering, Policy and Scheduling
2022-06-09HouseRules suspended
2022-06-09HouseRead second and ordered to a third reading
2022-07-06HouseRead third and passed to be engrossed
2022-07-06HouseEnacted
2022-07-14ExecutiveSigned by the Governor, Chapter 105 of the Acts of 2022

Public hearing

House Rule 27 counts its reporting deadline from the day a bill is heard.

DateCommitteeWhereStatus
2022-03-08State Administration and Regulatory Oversight (J)Virtual Hearing, 24 Beacon Street, BostonCompleted

Committee actions

ActionCommittee
FavorableState Administration and Regulatory Oversight (J)
Correctly DrawnBills in the Third Reading (S)
Place in ODSteering, Policy and Scheduling (H)
Correctly DrawnBills in the Third Reading (H)